Skip to main content
Construction works

Works and Service Notices

An update on the works taking place on the island and how they may impact your visit.

Works and service improvements are conducted periodically across Wadjemup / Rottnest Island

A range of projects are also currently underway to refresh and revitalise the island facilities. These works aim to enhance the visitor experience and to preserve the island long term.

Please refer to this list for updates on works taking place and how they may impact your visit.

For information on projects that are transforming the island, visit Significant Projects.

For further information on planning your visit to the island, visit rottnestisland.com.

Last updated: 5 December 2024

Commencing: 11 December 2024
Completion:
 12 December 2024

Ground Penetrating Radar (GPR) Survey scanning in and around houses along Kitson Street and behind the Rottnest Island Police Station. Minor impact to residents and police station.

Commencing: 9 December 2024
Completion:
 9 December 2024

Geotech investigation on the site works associated with the development of worker accommodation for The Lodge Wadjemup project. All works will be carried out on site, there will be no disruptions.

Commencing: 9 December 2024
Completion:
 10 December 2024

A new CCTV camera on a pole will be installed at the Visitor Centre end of the Main Jetty as part of the CCTV Upgrade Project (Phase 1 & 2).

These works include cutting into the concrete along the footpath to install a power conduit and will incur noise during the daytime only.

Commencing: 21 November 2024
Completion:
 December 2024

Installation of a new ticket booth at the Settlement bus stop. Bus services will not be disrupted and traffic management will be in place.

Commencing: 17 August 2024   
Completion: 28 March 2025 
 
The electrical network capacity on the island is being increased to support the expansion of the desalination plant and future developments. 

Cabling and electrical infrastructure works are part of the island-wide electrical network upgrades. Noise and heavy traffic will impact the fenced-off work areas. 

Commencing: 10 June 2024 
Completion: 13 December 2024 

To extend jetty life and enhance visitor safety and customer experience, the Main Jetty pavement will be resurfaced, while berths 1 to 3 are being replaced. 

Reconstruction will improve jetty access due to long term erosion, removing inconsistent ground levels and unsafe access to the island.

As part of the project the jetty pavement will be reconstructed and sealed with asphalt.

Berth access for ferry operators will be staggered with one berth closed at a time and ferry times re-scheduled to suit construction.  

For updates and information, refer to schedules on ferry operator websites, and signage on the Main Jetty and at the Visitor Centre. Fencing of works may also restrict visitor access with requirements to follow directions for safety at all times. 

Note: Boarding times may be reduced to accommodate fluctuating berth access.

Rottnest Island Authority is progressing the Ablution Facilities Upgrade Program, with facilities across the island scheduled to be upgraded over the coming years as part of the island’s capital works program.

Narrow Neck Ablutions Replacement and Precinct Upgrade 

Commencing: Mid-April 2024 
Completion: 13 December 2024

The new Narrow Neck Precinct and ablutions will include: 

  • Construction of new ablution block with hybrid septic system 
  • New bin enclosure area with vehicle turnaround
  • Bus stop improvements
  • Recreation area with bitumen stabilised limestone hardstand, shelters and picnic tables, and new vegetation.

Note: Demolition of old toilets will not commence until new toilets are operational.  

Commencing:  2 December 2024
Completion:  
20 December 2024

New barrier fencing is being installed at Discovery Rottnest accommodation to facilitate upgrades. Signage will be used to redirect pedestrians from within the resort and outside the resort. Minor noise is expected during the hours of 7 am and 5 pm on weekdays. 

Commencing: 21 November 2024
Completion:
 January 2026

Wadjemup was used as an Aboriginal prison and forced labour camp between 1838 and 1931. State records indicate that 4,000 Aboriginal men and boys from Western Australia were imprisoned on the island, including in the Quod. Heritage conservation works will conserve the building. Aboriginal monitors will be on site throughout the works.

The Quod will be fenced off during works and there will be some noise during the works.

Commencing: June 2023

Completion: September 2025

New food and beverage, accommodation and conference facilities for The Lodge Wadjemup are in progress.

Redevelopment includes new accommodation and refurbishment of 109 rooms including 46 new rooms and refurbishment of 31 Boys Reformatory rooms and 32 Lakeside Villas.

In addition, new food and beverage facilities including a kiosk, conference and event facilities, pools and amenities are under construction.

Stage 1
Completion: Late 2024
New restaurant set to open and refurbishment of the Boys Reformatory and Lakeside Villas.

Stage 2
Completion: September 2025
New poolside villas and conference facilities.

  • Noise and additional vehicle movements may occur during The Lodge Wadjemup redevelopment.
  • To ensure minimal disruption to visitors and the environment, Boreham Way will be closed with access only to contractors.
  • Public access remains open on Kitson Street, Digby Drive and surrounding Garden Lake.
  • Increased traffic is expected along Digby Drive, Brand Way, Parker Point Road and surrounding the aerodrome.
  • Vehicles involved in the works will need to travel during construction hours, Monday to Saturday.